首頁 > Job References > Hotel and Office > Guangzhou CTF Finance Centre (East Tower)
Guangzhou CTF Finance Centre (East Tower)
Project Name: Guangzhou CTF Finance Centre (East Tower)
Type: LV
Switch Qty: 22 x 3200A, 17 x 2500A, 35 x 2000A, 29 x 1600A, 22 x 1250A, 4 x 1000A, 9 x 800A
Installation: China Railway Construction Engineering Group Co., Ltd.
Design Institute/Consultant: Parsons Brinckerhoff (Asia) Ltd.
Completion Date: 6/2016
Type: LV
Switch Qty: 22 x 3200A, 17 x 2500A, 35 x 2000A, 29 x 1600A, 22 x 1250A, 4 x 1000A, 9 x 800A
Installation: China Railway Construction Engineering Group Co., Ltd.
Design Institute/Consultant: Parsons Brinckerhoff (Asia) Ltd.
Completion Date: 6/2016